Funding of grid connections in conjunction with charging infrastructure

Funding for grid connections for non-publicly accessible charging infrastructure at contiguous parking or garage complexes in NRW: 20% up to a maximum of €10,000. Applications possible until 31.12.2026.

Energy Efficiency & Renewable Energies Infrastructure

Discover your potential with AI support

  • Find out if this grant matches your project
  • Develop your application together with AI
  • Get matched with many more suitable grants

Grant criteria

Application Deadline:
01.02. - 31.12.2026
Application level: Advanced
Region: North Rhine-Westphalia
Funding amount: maximum €10,000
Funding rate: 20%
Project duration: 18 months

Funding objective

Grant for the technical connection of parking space or garage complexes to the power grid in order to support the expansion of electromobility through the development of necessary grid infrastructure.

Eligible expenses

  • Grid connections
  • Upgrading an existing grid connection
  • Construction cost subsidies
  • Cabling up to the distribution box
  • Necessary modifications to the distribution box
  • Show more

Non-eligible expenses

  • Charging infrastructure (charging station/wallbox)

Eligible to apply

  • Individuals
  • Companies
  • Interest Groups and Other Associations
  • Public Institutions

Funding requirements

  • locally contiguous parking space or garage complex with at least four parking spaces
  • age of garages or parking spaces at least two years
  • proof of installation of at least one non-publicly accessible stationary charging point with a minimum charging capacity of 11 kW
  • no more than one common grid connection per complex eligible for funding

Documents required for application

  1. Cost estimate
  2. Offer
  3. Proof of charging point (11 kW)
  4. Online application with PIN code

Evaluation criteria

  • Complex with at least four parking spaces
  • Minimum age of the parking spaces
  • Charging point verification

Description

The funding for grid connections in conjunction with charging infrastructure is aimed at property owners, municipalities, companies, associations, and clubs in North Rhine-Westphalia. The purpose of the grant is the technical connection of locally contiguous parking and garage complexes (at least four parking spaces, older than two years) to the power grid in order to supply non-publicly accessible charging points with a minimum charging capacity of 11 kW, thereby supporting the expansion of electromobility. The funding is provided as a co-financing of 20% of the eligible expenses, but no more than €10,000, and includes, among other things, grid connections, upgrades, civil engineering, foundations, cabling up to the distribution box, transformers, as well as necessary modifications to the distribution box. Only one joint connection per complex is subsidized.

Interested applicants must submit a cost estimate, proof of the stationary charging point, and PIN code procedure by December 31, 2026, via the electronic application form of the Arnsberg District Government. After a positive review, a grant approval notice will be issued, with which the measure can be commissioned and completed within 18 months. Subsequently, payment is made upon submission of the proof of use. A prerequisite for payment is the timely commissioning and execution of the work as well as compliance with the award and ancillary conditions (ANBest-P or ANBest-G). The measure may only be started after approval. This ensures transparent use of funds and a sustainable strengthening of the charging infrastructure in NRW.