Grant

ARF - New Railway Lines and Electrification of Regions (Koralmbahn)

Funding for the construction of new railway lines and electrification of regional railway lines in Carinthia and Styria within the framework of the EU Recovery and Resilience Facility NextGenerationEU. Valid from 01.02.2020 to 31.12.2026.

Infrastructure

Discover your potential with AI support

  • Find out if this grant matches your project
  • Develop your application together with AI
  • Get matched with many more suitable grants

Grant criteria

Application Deadline:
01.02. - 31.12.2026
Application level: Complex
Region: Carinthia, Styria
Funding amount: €542.6 million
Funding rate: 40%
Project start from: 01.02.2020
Project duration: 84 months

Funding objective

The measure "Construction of new railway lines and electrification of regional railways" aims to establish an approximately 130 km long electrified high-performance line between the state capitals Graz and Klagenfurt, as well as the electrification and expansion of regional lines in Carinthia and the connection to the Graz-Köflach Railway network.

Eligible expenses

  • Construction and planning costs
  • ETCS equipment
  • Electrification measures

Eligible to apply

  • Public Institutions

Funding requirements

  • Milestone 1: Start of construction Lavanttal station (Q1/2020)
  • Milestone 2: Commissioning of electrification of regional railway line + feeder line Carinthia including Lavanttal station and ETCS equipment (Q4/2023)
  • Milestone 3: Commissioning of Koralmbahn including entire feeder line Styria and Koralmtunnel including ETCS equipment (Q4/2025)

Description

Within the framework of the NextGenerationEU Recovery and Resilience Facility, an approximately 130 km long electrified high-performance rail line is being constructed between the state capitals Graz and Klagenfurt in Carinthia and Styria, and existing regional lines in Carinthia are being modernized. The objective of this measure is not only continuous electrification but also integration into the Graz-Köflach Railway network as well as equipping with modern ETCS signaling technology standards. With a total volume of €1.3657 billion, the federal government is investing in sustainable transport infrastructure until the end of 2026; of this, €542.6 million (funding rate 40%) is provided from the EU facility. The project strengthens both passenger and freight transport through shorter travel times and increased capacities and contributes to the reduction of CO₂ emissions. The measure is expected to be implemented in three phases: start of construction at Lavanttal station (Q1/2020), commissioning of electrification in Carinthia including ETCS (Q4/2023), and full commissioning of the Koralm Railway with tunnel (Q4/2025).

The ÖBB-Infrastruktur AG, as a public infrastructure operator, is eligible for funding; indirectly, all railway undertakings, public transport users, as well as the freight transport and logistics sectors benefit. Eligible expenses include construction and planning costs, ETCS equipment, and electrification measures. The project duration spans 84 months, applications can be submitted until 31.12.2026, and the project started on 01.02.2020. Through consistent implementation of milestones, rapid completion is ensured and the rail connection in the regions is expanded in a future-proof manner.